Filter
Numerical modelling study for disposal of treated effluent of 900 m3/ from 15000 BOPD plant at Cairn Oil & Gas facility, Suvali village, Hazira, Surat.
Duration : November 27, 2017 to March 31, 2018
Project Leader : Dr. Babu MT
Numerical modelling for studying the dredge dispersion pattern off Mormugao Bay
Duration : March 1, 2017 to October 31, 2018
Project Leader : Dr. Babu MT
Net Environmental Benefit Analysis (NEBA) for Oil spill risk contingency planning for Kandla and Vadinar Ports, Gujarat
Duration : November 9, 2015 to October 31, 2018
Project Leader : Dr. Babu MT
Environment Impact Assessment of the proposed marine outfall for the disposal of 20 MLD effluent from the STP at Baina, Goa
Duration : December 1, 2014 to March 31, 2016
Project Leader : Dr. Babu MT
Numerical modelling of the sediment transport around the seawater intake system for the 2x600MW Udupi power project: Part A-modelling studies
Duration : March 17, 2014 to June 30, 2016
Project Leader : Dr. Babu MT